Project Information

  • Client: Atomenergoproekt
  • General Designer: Atomenergoproekt
  • Contractor: Mostostroy No. 6
  • Contract Value: $5,000,000
  • Finish Date: August 2015

No. 2 of NVNPP-2

A complex of construction and installation works for the construction of the evaporative cooling tower of block 2 of NVNPP-2 and the cold water outlet channel of the cooling tower (turnkey).

  • 3500 Tons Steel Assembly Works
  • 20.000 m3 Reinforced Concrete Works
  • Height of structures - 171 m
  • Diameter at ground level - 135.31 m
  • Irrigation area - 11.000 m2

List of works, construction of a foundation pit, construction of a pile foundation, installation of a catchment slab, installation of hot water supply channels, balancing channels, installation of a circular foundation, installation of lifting shafts includes. , installation of the cooling tower shell, installation of internal supporting structures, installation of reinforced concrete columns of the supporting column, installation of technological equipment of the cooling tower.

OUR PARTNERS

Information Catalog

To have detailed information about Testko İnşaat, download and examine our catalogue